N |
Investment project title |
Development of production technology of the rust converter "LA-2" |
1. |
Sector |
Protection against corrosion of pipelines for water and natural gas supply, industrial constructions, transport vehicles, bridges made of ferrous metals |
2. |
Project description |
It is planned to upgrade the pilot production installation, to purchase the necessary raw materials, technological and laboratory equipment aimed at increasing the producing capacity (up to 300-500 ton/year), as well as involvement and training of experts. Besides, advertising activity will be widened. |
3. |
Project implementation period |
18 months |
4. |
Project location |
A. Nalbandyan Institute of Chemical Physics of NAS RA |
5. |
Project overall cost (USD) |
60.000 |
6. |
Required investments (USD) |
60.000 |
7. |
Own funds (USD) |
Pilot production area with equipment and setups, the developed technology of rust converter (substantiated by appropriate documentation and specification) |
8. |
Creation of jobs |
At the beginning of the project |
At the end of the project |
6 |
15 |
9. |
Payback period |
23-24 months |
10. |
Annual profitability index |
Correct annual profitability may be calculated after the project implementation. According to preliminary calculations profitabi |
11. |
Detailed costs |
- |
12. |
Offer to investor |
It is offered to conduct negotiations concerning cooperation in the case of implementation. |
13. |
Contact details |
Levon Tavadyan, Director of A.Nalbandyan Institute of Chemical Physics of NAS RA E-mail: tavadyan {[ at ]} ichph.sci.am Tel.: (+374 10) 281481 |